Silicon Valley Clean Water (SVCW) has provided notice that truck traffic will increase through September 20th along Redwood Shores Parkway.
Truck traffic along Redwood Shores Parkway will be greater than anticipated for approximately a four-week period starting the week of August 21, 2017. The increased traffic is being used to reduce the duration and overall impact of heavy truck traffic, for site preparation improvements at Silicon Valley Clean Water, on residents and businesses along Redwood Shores Parkway and Radio Road.
The project originally envisioned 50 truck trips per day. The contractor anticipates they will be using 150 truck trips per day to bring soil to the site. It is anticipated that delivery of the soil can be completed as early as September 20th. The trucks are required to drive in the right-hand lane and to obey the posted 25 mph speed limit.
For additional information, please see Silicon Valley Clean Water’s full notice.